Ministry of Transportation has approved the Investors appointment results for the Expand National Road 1A through Quang Ngai in the form of BOT.
The investment construction expand 1A National Road Project have the starting point from La Ha bridge, La Ha town, Tu Nghia district (connecting with the tail of High way Da Nang – Quang Ngai with National Road 1A) to the tail of Pho Ninh town area, Duc Pho district.
Many downgraded streets on 1A National Road through Quang Ngai need to be upgrade, expand. Images: Tri Tin
Project has the total budget nearly 2.140 billion VND. Investor was appointment as Joint venture between Thien Tan Investment Construction Joint Stock Company and Thanh An Corporation (Ministry of National Security)
The expansion have 29,5km in length, each side is expand more than 5,5m, total roadway width is 22m, median strips in the middle for 4 lanes of cars; repair, build 12 small, medium bridges. Toll station is expected to be built outside of the Cat bridge, Nghia Thuong commune, Tu Nghia District.
Mr.Huynh Kim Lap, Director of Thien Tan Investment Construction Joint Stock Co., representative of Owner said: “Construction will be groundbreaking on 9th of June, expected to be complete in the end of 2015”.
Tri Tin – According to Vnexpress