Press the damming buttons
Attending the ceremony were Mr.Pham Dinh Khoi – Provincial Secretary; Mr.Nguyen Hoa Binh – Provincial Deputy Secretary; Mrs. Truong Thi Xuan Hong – Vice Chairman of Quang Ngai province; Mrs.Dinh Thi Loan – Vice Chairman of Quang Ngai province; representatives of Departments and leaders, people of Tra Thuy commune, Tra Bong district…
Ha Nang hydropower has the total budget of over 330 billion VND, Owner by Thien Tan Investment Construction Joint Stock company (B.O.O). Construction will begin from April-2008, total generation capacity is 11MW.
Mr.Huynh Kim Lap – Director of Thien Tan Investment Construction Joint Stock company give 25 million VND to Gratitude Fund
After 15 months of construction, company and contractors have constructed over 1,5 million m3, crafting 12.000 tons of equipments. Particularly, Ha Nang main dam soil embankment is over 700.0003. The main dike has 39m height and 350m length.
To stablize the life for people in Project area, Company has built 104 4A house for 104 ethnic minorities in Tra Thuy commune (avarage compensation per household is 100 million VND), constructed 20 km of roads, facilitate for transportation and economic development of people.
At this time, Projects has complete 80%. It is expected that at the end of December-2009, the plant will be completed and officially connect to national grid.
At the ceremony, Thien Tan Investment Construction Joint Stock company had contributed 25 million VND to Gratitude Fund of Tra Bong district. People’s Committee has awarded certificate of merit for 3 individuals of Thien Tan Investment Construction Joint Stock company for achivement in speeding up the construction progress of Ha Nang hydropower plant.
News, pictures: M.Toan (Quang Ngai newspaper)